A specialized excavator dredges an approach channel at B.C. Hydro's Site C project on the Peace River in northeast B.C.

Courtesy of Site C Clean Energy Project

Restrictions imposed by British Columbia to fight the spread of COVID-19 infections after the holiday break have disrupted work at construction sites of a Rio Tinto hydropower project and BC Hydro’s Site C dam.

A total of five major industrial projects in remote northwestern Canada have been affected as the provincial government last week ordered them to stagger the return of their workers after the Christmas holiday break.

BC Hydro’s Site C dam, Rio Tinto’s Kemano T2 hydropower project, the Trans Mountain pipeline expansion, TC Energy’s Coastal GasLink pipeline and the Royal Dutch Shell-led LNG Canada project are named in the order.

Story continues below advertisement

The companies did not say how the slow return of workers would impact ultimate completion dates for their projects.

Across the five projects the number of workers will ramp up from a baseline of 1,460 to 4,080 by mid-February.

Provincial health officer Dr Bonnie Henry said a rapid return to full operating capacity after Christmas would likely “fuel and accelerate” the spread of COVID-19 among workers and surrounding communities.

“While these changes will have a further impact on our overall project schedule and cost, we understand the rationale for the order,” said David Conway, spokesman for the $10.7 billion Site C project on the Peace river, which is already over budget.

Rio Tinto’s Kemano T2 project, in which a second tunnel is being built to provide hydropower to the BC Works aluminum smelter in Kitimat, would normally have 330 workers on site but will be limited to 280 until further notice.

Rio Tinto expects the project to resume operations when it is authorized “to increase the number of workers onsite to safely operate the tunnel boring machine,” a company spokesman said.

The Canadian government-owned Trans Mountain project halted work on the pipeline expansion in December after multiple safety issues.

Story continues below advertisement

Construction was meant to restart on Monday but is still paused, although Trans Mountain did not say whether the new COVID-19 rules had caused the delay. The 1,150-kilometer pipeline carries crude from Alberta across British Columbia to the coast and the order only affects one work camp in Valemount.

“We are in the final stages of our restart planning and anticipate that we will be providing further details on restart dates in the coming days,” a Trans Mountain spokeswoman said on Tuesday.

An LNG Canada spokesman said the slower return to work schedule would enable the project to keep going with “seasonally critical” work. Coastal GasLink did not immediately respond to a request for comment.

Your time is valuable. Have the Top Business Headlines newsletter conveniently delivered to your inbox in the morning or evening. Sign up today.

Your Globe

Build your personal news feed

  1. Follow topics and authors relevant to your reading interests.
  2. Check your Following feed daily, and never miss an article. Access your Following feed from your account menu at the top right corner of every page.

Follow topics related to this article:

View more suggestions in Following Read more about following topics and authors
Report an error
Tickers mentioned in this story
Due to technical reasons, we have temporarily removed commenting from our articles. We hope to have this fixed soon. Thank you for your patience. If you are looking to give feedback on our new site, please send it along to feedback@globeandmail.com. If you want to write a letter to the editor, please forward to letters@globeandmail.com.

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff.

We aim to create a safe and valuable space for discussion and debate. That means:

  • Treat others as you wish to be treated
  • Criticize ideas, not people
  • Stay on topic
  • Avoid the use of toxic and offensive language
  • Flag bad behaviour

If you do not see your comment posted immediately, it is being reviewed by the moderation team and may appear shortly, generally within an hour.

We aim to have all comments reviewed in a timely manner.

Comments that violate our community guidelines will not be posted.

UPDATED: Read our community guidelines here

Discussion loading ...

To view this site properly, enable cookies in your browser. Read our privacy policy to learn more.
How to enable cookies