The Canada Border Services Agency (CBSA) said on Friday that the modules to be used in a liquefied natural gas export terminal near Vancouver should be subject to hefty import tariffs on certain steel elements, in a blow to the proposed $1.6-billion project.

In its decision, the CBSA said the fabricated industry steel components (FISC) of an LNG module are not transformed when non-FISC elements are connected, and therefore the 45.8 per cent anti-dumping tariffs on the FISC portion should apply.

Woodfibre LNG has estimated that FISC makes up roughly 40 per cent by weight of the modules it plans to use to build its LNG export plant.

Story continues below advertisement

“We’re reviewing the ruling and evaluating our options,” said Jennifer Siddon, a spokeswoman for the company, without providing further details on Woodfibre’s next steps.

Woodfibre applied for the CBSA scope proceeding in June, in hopes the border agency would determine its modules were not covered in a 2017 ruling by a Canadian trade court that found certain FISC from China, South Korea and Spain were being dumped into the Canadian market, harming local producers.

Woodfibre argued that its modules should not be subject to the tariffs as they are not basic steel structures, but rather manufactured goods that include “a myriad of complex and specialized machinery.” It said applying the tariffs to its FISC modules would be like applying sugar tariffs to the import of bottled soda.

Woodfibre is backed by Indonesian billionaire Sukanto Tanoto’s RGE Group.

Woodfibre and the companies behind other Canadian projects have further argued that LNG modules are complex units that have never been built domestically, with the vast majority of global production concentrated in specialized steel yards in Asia.

The CBSA said Woodfibre could appeal its decision to the Canadian International Trade Tribunal (CITT), which made the original ruling.

The original CITT ruling is currently being considered in Canada’s Federal Court of Appeal, with a decision expected some time this year.

Story continues below advertisement

Construction is expected to start on Woodfibre LNG early next year, with first shipments in 2023. The plant, located some 60 kilometres (37 miles) north of Vancouver, will liquefy and export some 2.1 million tonnes of supercooled gas each year.

Report an error
Comments

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff.

We aim to create a safe and valuable space for discussion and debate. That means:

  • All comments will be reviewed by one or more moderators before being posted to the site. This should only take a few moments.
  • Treat others as you wish to be treated
  • Criticize ideas, not people
  • Stay on topic
  • Avoid the use of toxic and offensive language
  • Flag bad behaviour

Comments that violate our community guidelines will be removed. Commenters who repeatedly violate community guidelines may be suspended, causing them to temporarily lose their ability to engage with comments.

Read our community guidelines here

Discussion loading ...

Due to technical reasons, we have temporarily removed commenting from our articles. We hope to have this fixed soon. Thank you for your patience. If you are looking to give feedback on our new site, please send it along to feedback@globeandmail.com. If you want to write a letter to the editor, please forward to letters@globeandmail.com.
Cannabis pro newsletter