On the eve of an election call, Quebec’s main party leaders have gone to battle over a wind-power project that Liberal Premier Philippe Couillard argues is crucial to good relations with First Nations but that François Legault’s Coalition Avenir Québec calls “useless” and “ruinous.”

The head of Hydro-Québec, which would purchase all of the power from the 200-megawatt Apuiat wind-energy development on Quebec’s remote North Shore, has warned that the project would cause losses of between $1.5-billion and $2-billion for the provincial utility over 25 years.

The warning from Hydro-Québec chief executive officer Éric Martel, contained in a letter obtained last week by Le Journal de Montréal, drew a stiff rebuke from Mr. Couillard and Quebec Energy Minister Pierre Moreau. They ordered Mr. Martel to put a sock in it and negotiate a long-term power purchase contract with the Innu First Nation and its partners in the $600-million Apuiat project, Quebec’s Boralex Inc. and Le Groupe RES of France.

Story continues below advertisement

Mr. Martel’s position, Mr. Moreau said in a reply to the utility’s CEO, “is contrary to the direction and objectives that the government of Quebec has set for Hydro-Québec, of which, I will remind you, it is the sole shareholder.”

The controversy over the Apuiat project has rekindled a debate about the role of wind energy in Quebec’s electricity mix, of which more than 90 per cent comes from decades-old hydroelectricity dams owned directly by Hydro-Québec or from the partly owned Churchill Falls project in Labrador. These so-called legacy projects have left Hydro-Québec with among the lowest production costs in North America, allowing the province to maintain residential and industrial electricity rates that are the envy of its neighbours, especially Ontario.

Critics warn, however, that this competitive edge is being slowly frittered away by government moves to use Hydro-Québec as a cash cow to backstop politically motivated wind-power projects.

The former Liberal government of Jean Charest ordered Hydro-Québec to enter long-term purchase contracts with private renewable-power producers at prices far above the utility’s own cost of production. In May, Quebec Auditor-General Guylaine Leclerc concluded these contracts, largely for wind power, boosted Hydro-Québec’s costs by $2.5-billion between 2009 and 2016.

While the cost of wind energy is rapidly declining across North America, the Apuiat project’s developers would still reportedly fetch around 10 cents per kilowatt-hour for their power. That compares with the production costs of about 2.9 cents a kwh for Hydro-Québec’s legacy dams and about 6.5 cents a kwh for the 1,500-MW Romaine generating station now nearing completion.

With Romaine now mostly on-stream, the utility is sitting on large energy surpluses for years to come. Hydro-Québec’s attempts to unload its surpluses through long-term power purchase contracts with U.S. buyers have been stymied by competition from cheap natural-gas-generated power and environmentalist opposition to big hydro projects, as well as the new transmission lines the utility needs to send additional power south. As a result, Hydro-Québec’s power exports mostly consist of short-term sales in the U.S. spot market. Export sales generated a profit of $780-million in 2017, or about a quarter of the utility’s overall profit of $2.85-billion.

For Mr. Couillard, the Apuiat project is crucial to obtaining Innu support for future hydro, mining and other development on their traditional territory. “Do you think First Nations are going to continue to accept the use of their territory to develop [Quebec’s] wealth without them getting an appreciable and visible part of it?” the Premier insisted on Saturday.

Story continues below advertisement

Indeed, the Pessamit Innu Nation has lobbied officials in Massachusetts to reject Hydro-Québec’s bid to sell power from the Romaine project to utilities in the state. “Hydro-Québec has destroyed our territories,” Chief René Simon told the Boston Globe in January. “I would advise the Governor of Massachusetts not to buy power from Hydro-Québec."

The nine Innu communities on Quebec’s North Shore remain united in supporting the Apuiat, even if critics suggest Boralex and RES will be the main beneficiaries of the project. The development would create between 300 and 400 jobs during the construction phase, but only about 15 full-time jobs once it is completed.

For his part, Mr. Legault argues that no new wind-energy deals should be authorized until Hydro-Québec secures new long-term contracts to sell its power in U.S. markets. “Citizens of the North Shore might be deprived of a project in the short term. But they will understand that we can’t force $1.5-billion in losses on Hydro-Québec to create jobs. The jobs need to be useful,” the CAQ Leader said on the weekend.

Quebec’s election campaign is set to kick off on Aug. 23 and Mr. Legault has warned the Premier against forcing Hydro-Québec to sign a purchase agreement on Apuiat before the Oct. 1 election. But that is precisely what Mr. Couillard and Mr. Moreau appear to have ordered Hydro-Québec to do, with the utility set to resume negotiations with the Innu on Wednesday. Mr. Martel’s future, needless to say, hangs in the balance.

Report an error Editorial code of conduct
Comments

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff.

We aim to create a safe and valuable space for discussion and debate. That means:

  • All comments will be reviewed by one or more moderators before being posted to the site. This should only take a few moments.
  • Treat others as you wish to be treated
  • Criticize ideas, not people
  • Stay on topic
  • Avoid the use of toxic and offensive language
  • Flag bad behaviour

Comments that violate our community guidelines will be removed. Commenters who repeatedly violate community guidelines may be suspended, causing them to temporarily lose their ability to engage with comments.

Read our community guidelines here

Discussion loading ...

Due to technical reasons, we have temporarily removed commenting from our articles. We hope to have this fixed soon. Thank you for your patience. If you are looking to give feedback on our new site, please send it along to feedback@globeandmail.com. If you want to write a letter to the editor, please forward to letters@globeandmail.com.
Cannabis pro newsletter