Energy and Resources Enbridge’s Line 3 pipeline replacement likely won’t be in service until second half of 2020

A pipeline that Alberta has been counting on to ease the bottleneck in moving its crude oil to foreign markets won’t be in service for at least another year, six months later than expected, according to its owners.

Enbridge Inc. says in a news release that the timeline for construction of the Line 3 replacement likely won’t see the pipeline operational until the second half of 2020.

Just two weeks ago, the Calgary-based company expressed confidence that the project would be in service by the end of this year.

Story continues below advertisement

But Enbridge now says it is revising its construction schedule, following information provided by the State of Minnesota on Friday about its timeline for granting remaining environmental permits.

Enbridge says the state indicates the permits should be available by November, and the company anticipates the remaining federal permits it needs will be finalized approximately 30 to 60 days later.

The project will transport crude from Alberta to Wisconsin, where it will connect with pipelines to the U.S. Gulf Coast. It’s designed to replace an aging pipeline and restore its original capacity of 760,000 barrels per day, an increase of about 370,000 bpd.

“We now have a firm schedule from the state on the timing of the remaining permits for our Line 3 Replacement project,” Enbridge CEO Al Monaco said in a statement.

“We support a robust and transparent permitting process that includes opportunity for public input. We’ll continue to work closely with state officials during this process.”

The company says more specific timing on the in-service date, as well as any potential impacts on its 2020 financial outlook, will be provided once the revised construction schedule is finalized.

A lack of export pipeline space was blamed for steep discounts in western Canadian oil prices last year, leading to production curtailments by the Alberta government that began Jan. 1.

Story continues below advertisement

Premier Rachel Notley said when she announced the cuts that they would last until Dec. 31, 2019 — when Line 3 was expected to be up and running.

Two other pipelines, the Trans Mountain expansion and the Keystone XL project, are both in limbo after being stalled by court decisions in Canada and the U.S.

Mike McKinnon, a spokesman for Alberta’s Energy Minister, acknowledged in an email that the delay in Line 3 was a “setback” but said the government is confident the pipeline will be completed.

Mr. McKinnon also defended the NDP government’s decision last month to lease tanker cars to ship its oil by rail — a move criticized by Opposition Leader Jason Kenney of the United Conservatives as being too risky.

“As we lead the charge for pipelines, this kind of uncertainty is exactly why we have a plan to move more oil by rail until new pipelines are built, and we call on Jason Kenney to stop his reckless attempt to sabotage this plan for his own political self-interest,” Mr. McKinnon wrote.

“We need to move more of our product, not produce less.”

Story continues below advertisement

Last month, Minnesota Governor Tim Walz announced that his Commerce Department would petition the state Public Utility Commission to reconsider its approval of Line 3 through Minnesota, prolonging a process begun by his predecessor.

Previous challenges by the former governor were set aside by the commission.

Report an error
Tickers mentioned in this story
Unchecking box will stop auto data updates
Due to technical reasons, we have temporarily removed commenting from our articles. We hope to have this fixed soon. Thank you for your patience. If you are looking to give feedback on our new site, please send it along to feedback@globeandmail.com. If you want to write a letter to the editor, please forward to letters@globeandmail.com.

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff.

We aim to create a safe and valuable space for discussion and debate. That means:

  • Treat others as you wish to be treated
  • Criticize ideas, not people
  • Stay on topic
  • Avoid the use of toxic and offensive language
  • Flag bad behaviour

Comments that violate our community guidelines will be removed.

Read our community guidelines here

Discussion loading ...

Cannabis pro newsletter