Energy and Resources Line 3 pipeline delays make oil sands expansion unlikely, MEG Energy CEO says

The CEO of MEG Energy Corp. says a one-year delay in Enbridge Inc.’s Line 3 pipeline replacement project makes it highly unlikely it will approve an option to spend about $75-million to complete an expansion of its Christina Lake oil sands project in northern Alberta.

Derek Evans says about 60 per cent of the $275-million cost of the expansion has already been invested and it will take about a year to bring into production once approved, but there’s no point in doing so if there’s no pipeline capacity to carry the oil to market.

Last week, Enbridge said permitting delays in Minnesota meant its Line 3 project, expected to add 370,000 barrels per day of export capacity of Canadian crude, won’t open until the second half of 2020, a year later than expected.

Story continues below advertisement

The MEG expansion would allow production capacity to climb to about 113,000 barrels per day from the current 100,000.

MEG shares fell by as much as 9.7 per cent to $4.75 in early trading on the Toronto Stock Exchange after it reported an operating loss of $118-million in the fourth quarter compared with an operating profit of $44-million in the same period of 2017.

It blamed the bigger loss on discounts on western Canadian crude as its average realized bitumen price fell to $13.90 per barrel from $48.30.

The company says it expects to double its crude-by-rail volumes to 30,000 barrels per day by next fall from 14,700 in the last three months of 2018.

Report an error
Due to technical reasons, we have temporarily removed commenting from our articles. We hope to have this fixed soon. Thank you for your patience. If you are looking to give feedback on our new site, please send it along to feedback@globeandmail.com. If you want to write a letter to the editor, please forward to letters@globeandmail.com.

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff.

We aim to create a safe and valuable space for discussion and debate. That means:

  • Treat others as you wish to be treated
  • Criticize ideas, not people
  • Stay on topic
  • Avoid the use of toxic and offensive language
  • Flag bad behaviour

Comments that violate our community guidelines will be removed.

Read our community guidelines here

Discussion loading ...

Cannabis pro newsletter