Aecon partnership named preferred proponent for Site C generating station

Work on the Site C dam in British Columbia.


A partnership led by Aecon Group Inc. has been chosen as the preferred proponent by BC Hydro for a Site C generating station and spillways civil works contract.

The work is expected to include civil works associated with the powerhouse, penstocks, spillways and power intakes, plus related ancillary construction work, the company says.

The full contract award is expected to take place early next year, with work to begin in the spring.

Story continues below advertisement

Aecon holds a 30 per cent stake in the partnership, while Dragados Canada Inc. has 27.5 per cent, Flatiron Constructors Canada Ltd. has 27.5 per cent and EBC Inc. holds 15 per cent.

The B.C. NDP government announced last week that it would complete the controversial hydroelectric dam rather than cancel the project.

The province's independent energy regulator concluded in a report last month that the dam is over budget and behind schedule.

B.C. Premier says the best decision for the future of the province is to complete the controversial Site C hydroelectric dam The Canadian Press
Report an error
Tickers mentioned in this story
Unchecking box will stop auto data updates
As of December 20, 2017, we have temporarily removed commenting from our articles as we switch to a new provider. We are behind schedule, but we are still working hard to bring you a new commenting system as soon as possible. If you are looking to give feedback on our new site, please send it along to If you want to write a letter to the editor, please forward to