var select={root:".js-sub-pencil",control:".js-sub-pencil-control",open:"o-sub-pencil--open",closed:"o-sub-pencil--closed"},dom={},allowExpand=!0;function pencilInit(o){var e=arguments.length>1&&void 0!==arguments[1]&&arguments[1];select.root=o,dom.root=document.querySelector(select.root),dom.root&&(dom.control=document.querySelector(select.control),dom.control.addEventListener("click",onToggleClicked),setPanelState(e),window.addEventListener("scroll",onWindowScroll),dom.root.removeAttribute("hidden"))}function isPanelOpen(){return dom.root.classList.contains(select.open)}function setPanelState(o){dom.root.classList[o?"add":"remove"](select.open),dom.root.classList[o?"remove":"add"](select.closed),dom.control.setAttribute("aria-expanded",o)}function onToggleClicked(){var l=!isPanelOpen();setPanelState(l)}function onWindowScroll(){window.requestAnimationFrame(function() {var l=isPanelOpen(),n=0===(document.body.scrollTop||document.documentElement.scrollTop);n||l||!allowExpand?n&&l&&(allowExpand=!0,setPanelState(!1)):(allowExpand=!1,setPanelState(!0))});}pencilInit(".js-sub-pencil",!1); // via darwin-bg var slideIndex = 0; carousel(); function carousel() { var i; var x = document.getElementsByClassName("subs_valueprop"); for (i = 0; i < x.length; i++) { x[i].style.display = "none"; } slideIndex++; if (slideIndex> x.length) { slideIndex = 1; } x[slideIndex - 1].style.display = "block"; setTimeout(carousel, 2500); } //

Toronto-based Barrick said it has opted to vastly scale back capital spending in 2013 and in 2014 on the Pascua-Lama project in South America.

Barrick Gold Corp. has gained some breathing room with its decision to delay development of its Pascua-Lama project, but the company faces pressure to shrink its global mining operations amid tumbling metal prices.

Barrick says first production from the South American gold and silver venture will be postponed by more than 18 months, as the Canadian company forecasts taking a writedown of up to $5.5-billion (U.S.) on the project.

Toronto-based Barrick said it has opted to vastly scale back capital spending this year and in 2014 on the project, which is located in the Andes mountains and straddles the border between Chile and Argentina.

Story continues below advertisement

While construction of the $8.5-billion project has suffered another setback, the venture remains strategically important to the world's largest gold producer, analysts say.

"With all this talk about what Barrick could look like in the future, Pascua-Lama will be key to the company's future operational performance, especially if Barrick wants to shed high-cost mines," said Chris Thompson, a Vancouver-based mining analyst at Raymond James Ltd.

Even though Pascua-Lama has enormous upfront capital costs, Barrick is drawn to the prospective rewards. There are an estimated 17.9 million ounces of proven and probable gold reserves, as well as 676 million ounces of silver, in the deposit.

Amid declining gold and silver prices, Barrick said it plans to "resequence construction of the process plant and other facilities in Argentina in order to target first production by mid-2016" – a delay of more than 18 months. Barrick had been aiming for a launch in the second half of 2014, though analysts interpreted that to mean late 2014, at best.

With Barrick committed to the South American venture in the long term, analysts say the company will be in a position to run fewer mines worldwide, potentially jettisoning operations with high operating costs.

Hours before Barrick made its announcement late Friday, credit rating agency DBRS placed the gold producer's debt under review, with negative implications.

In February, Barrick wrote down $3.8-billion of its 2011 investment in Equinox Minerals Ltd. Barrick had acquired Equinox for $7.5-billion, but the prized Lumwana copper mine in Zambia drained cash as extraction costs rose.

Story continues below advertisement

Since last September, gold prices have tumbled by 31 per cent to $1,230 an ounce while copper prices have declined by 20 per cent to $3 a pound, hammering the global mining industry and triggering a series of massive writedowns.

The commodity market's slump has raised questions about "Barrick's ability to restrain its debt burden in the face of ongoing cost pressures and capital expenditure requirements," DBRS warned.

DBRS also cautioned that Barrick had net debt of $12.5-billion on March 31, soaring from $2.7-billion at the end of 2010.

An after-tax asset impairment charge of between $4.5-billion and $5.5-billion is envisaged for the second quarter, due to the woes at Pascua-Lama. Other assets, including goodwill, could have impairment charges after further review.

Capital spending at Pascua-Lama is forecast to be chopped by a total of $1.5-billion to $1.8-billion in the 2013-14 time frame. That will translate into capital expenditures at the project of roughly $2-billion this year and potentially $1.2-billion next year, at the upper end of the range.

"In light of the challenging business environment we are facing today, and taking into consideration existing construction delays, the company is advancing the project in a prudent manner by extending the construction schedule over a longer period," Barrick chief executive officer Jamie Sokalsky said in a statement.

Story continues below advertisement

Mr. Sokalsky replaced Aaron Regent as CEO in June, 2012, when John Thornton was named co-chairman by Peter Munk, Barrick's founder and chairman. But the shakeup has done little to assuage concerns among some major shareholders seeking improved corporate governance, notably a call for new independent directors.

Pascua-Lama, which is already half-built, has been dogged by a series of delays.

In early April, a preliminary court injunction led to the suspension of construction work on the open-pit mine in Chile. In May, Chile's environmental regulator ordered Barrick to complete a water management system to prevent potential contamination.

Barrick expects to meet the regulator's demands to protect Chilean water supplies, aiming for completion by the end of 2014.

Barrick's stock price has plunged by 53 per cent this year.

Your Globe

Build your personal news feed

  1. Follow topics and authors relevant to your reading interests.
  2. Check your Following feed daily, and never miss an article. Access your Following feed from your account menu at the top right corner of every page.

Follow the author of this article:

View more suggestions in Following Read more about following topics and authors
Report an error Editorial code of conduct
Tickers mentioned in this story
Due to technical reasons, we have temporarily removed commenting from our articles. We hope to have this fixed soon. Thank you for your patience. If you are looking to give feedback on our new site, please send it along to feedback@globeandmail.com. If you want to write a letter to the editor, please forward to letters@globeandmail.com.

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff. Non-subscribers can read and sort comments but will not be able to engage with them in any way. Click here to subscribe.

If you would like to write a letter to the editor, please forward it to letters@globeandmail.com. Readers can also interact with The Globe on Facebook and Twitter .

Welcome to The Globe and Mail’s comment community. This is a space where subscribers can engage with each other and Globe staff.

We aim to create a safe and valuable space for discussion and debate. That means:

  • Treat others as you wish to be treated
  • Criticize ideas, not people
  • Stay on topic
  • Avoid the use of toxic and offensive language
  • Flag bad behaviour

If you do not see your comment posted immediately, it is being reviewed by the moderation team and may appear shortly, generally within an hour.

We aim to have all comments reviewed in a timely manner.

Comments that violate our community guidelines will not be posted.

UPDATED: Read our community guidelines here

Discussion loading ...

To view this site properly, enable cookies in your browser. Read our privacy policy to learn more.
How to enable cookies