Skip to main content

Capstone Mining's Yukon operations are see in this file photo. The company said Wednesday that the life of its Pinto copper mine in Arizona has been extended by eight years.CHRIS WATTIE/Reuters

Capstone Mining Corp. (TSX:CS) says a new pre-feasibility study on its wholly-owned Pinto Valley copper mine in Arizona has extended the mine's life by eight years to 2026.

The company, which bought Pinto Valley last year, says average annual production for the first five years is targeted at 128.4 million pounds of copper in concentrate and 6.6 million pounds of copper cathode.

Annual production for the life of the mine is 119.5 million pounds of copper in concentrate plus 6.3 million pounds of cathode copper.

The after-tax value, discounted at eight per cent, is US$738-million while capital costs are estimated to be $187.9-million over roughly 12 years.

In April 2013, Capstone Mining announced it would buy the Pinto Valley mine and the associated San Manuel Arizona Railroad Co. in Arizona from a subsidiary of BHP Billiton for US$650-million.

The life of the mine, located in Arizona's Globe-Miami mining district, about 125 kilometres east of Phoenix, was initially expected to stretch until 2018.

"Completion of the (pre-feasibility study) ... provides us with the platform to stabilize operations, gain efficiencies and gives us the opportunity to take a longer-term view towards the future of the Pinto Valley mine," said president and CEO Darren Pylot.

"As well as pursuing operating efficiencies, we have started the work required to evaluate a possible mine life extension beyond 2026 and a potential increase in throughput."

Report an editorial error

Report a technical issue

Tickers mentioned in this story

Study and track financial data on any traded entity: click to open the full quote page. Data updated as of 28/03/24 4:15pm EDT.

SymbolName% changeLast
BHP-N
Bhp Billiton Ltd ADR
+0.28%57.69
CS-T
Capstone Mining Corp
+2.38%8.62

Interact with The Globe