Enbridge Inc. said on Wednesday its Line 3 pipeline replacement project will begin operating on Oct. 1, the first successful major expansion of Canadian crude export capacity in six years, clearing hurdles that other projects were unable to overcome.

Its completion is welcome news for the Canadian energy sector after a number of proposed pipelines, including TC Energy Corp.’s Keystone XL, were scrapped because of environmental opposition and regulatory delays.

The US$8.2-billion project allows Enbridge to roughly double its capacity to 760,000 barrels a day on the 1,765-kilometre-long pipeline.

Line 3, built in the 1960s, carries oil from Edmonton to refineries in the U.S. Midwest, but for years was transporting less than its capacity because of age and corrosion. The project was opposed by environmental and Indigenous groups, particularly in Minnesota, the last stage of the expansion.

Construction in both Canada and the United States took more than seven years to finish, but the project succeeded where other projects have run aground because it was replacing an old line, rather than one starting from scratch, Leo Golden, Enbridge’s vice-president of Line 3 project execution, told Reuters in an interview.

“This was a safety-driven project about replacing existing, aging infrastructure so that set it apart from some of those other projects,” Mr. Golden said.

The 542-km Minnesota section of Line 3 is the last part of the pipeline to come in service, after already-completed segments in Canada, North Dakota and Wisconsin.

Mr. Golden said Enbridge will start filling the line on Oct. 1 and offer full capacity of 760,000 b/d in November. Earlier this month, the company told shippers it would offer 620,000 b/d of crude capacity in October.

He said that in the future adding capacity through optimizing and expanding existing pipelines would likely be the way the industry goes, given the challenges around building new infrastructure, a view echoed by trade union leaders in the U.S.

“The maintenance industry is our future, the lifeline of the oil and gas [pipeline] industry,” said Phillip Wallace, business representative for Pipeliners Union 798, which worked on the project in Minnesota. “Line 3 was the big boy that needed replacing badly.”

The finished project assures Canadian producers their growing oil sands crude output will have access to U.S. markets and global exports via the U.S. Gulf Coast.

Line 3 is the first major Canadian oil pipeline expansion to be completed since Enbridge’s Alberta Clipper project, finished in 2015. However, since 2019 Enbridge has also optimized parts of its existing Mainline system, adding roughly 150,000 b/d of capacity.

HUGE BOOST

The Line 3 replacement project was first announced in 2014 but ran into fierce opposition from environmental groups and First Nations, particularly in Minnesota.

U.S. President Joe Biden, who revoked a key permit for the Keystone XL pipeline earlier this year, has been criticized by some environmental groups for allowing the project to proceed. They argue the U.S. should be reducing its dependence on fossil fuels to fight climate change.

“President Biden and the other politicians who chose to do nothing as treaty rights were violated, waterways were polluted, and peaceful protesters were brutalized have placed themselves on the wrong side of history,” Sierra Club spokesperson Margaret Levin said in a statement.

However, the project was celebrated by trade unions, whose members benefited from thousands of jobs during construction, and Canada’s energy sector, which in the past has struggled with pipeline bottlenecks that depressed the price of Canadian crude and contributed to an exodus of foreign capital.

“This is a huge boost to the industry,” said Martin King, an analyst at RBN Energy. He said projected growth in Canada’s oil sands suggests the industry will need only one more major pipeline expansion, which will be the Canadian government-owned Trans Mountain expansion to the west coast.

Robert Fitzmartyn, head of energy research at Stifel FirstEnergy, said he expected Line 3′s completion to have a positive impact on Canadian oil company shares in the long-term.

Be smart with your money. Get the latest investing insights delivered right to your inbox three times a week, with the Globe Investor newsletter. Sign up today.

Report an editorial error

Report a technical issue

Tickers mentioned in this story

Study and track financial data on any traded entity: click to open the full quote page. Data updated as of 25/04/24 4:00pm EDT.

SymbolName% changeLast
ENB-T
Enbridge Inc
+1.35%49.52
ENB-N
Enbridge Inc
+1.68%36.26

Follow related authors and topics

Authors and topics you follow will be added to your personal news feed in Following.

Interact with The Globe